Construction Update for Week Beginning: 3/20/23

Language Arts Complex - Measure M:
Construction activity continues with interior painting, and installation of casework, ceilings, doors/hardware, and flooring. Exterior finishing continues with porcelain tile, terra cotta, and metal panel installation. Site work and grading may commence depending on rain; if site work is possible, use caution around heavy equipment entering Parking lot C. Work in manholes in front of the Bookstore and in the area behind the Bookstore continues intermittently. Please watch for barricades around open manholes and use caution in these areas. Portions of Parking Lot C remain barricaded for construction traffic; there is no parking within the barricades. Please watch for and obey the flagmen in this area. Roads and walkways within fenced off construction areas are not accessible to pedestrian traffic; please use alternate routes to get around Campus. Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be low for these activities. (See attached map [PDF] for work areas and construction vehicle routes)

Technology Bldg Irrigation/Landscape Improvement Project - Campus:
Work continues on the irrigation and vegetation upgrade in the area surrounding the Technology Bldg this week. Exercise caution around this area and stay clear of landscaping equipment/activity. Noise level will be moderate to high for these activities. (See attached map [PDF] for work areas)

Non-Campus Event- Campus:
The Parking lot between entrances D and E (corner of Goldenwest st. and Edinger ave.) will be blocked off for a non-campus event from Tuesday 3/21 through early morning Friday 3/24. There will be no campus parking allowed in this entire area until after the clean-up is finished on Friday morning. (See attached map [PDF] for event areas)

Forum 1 Painting Project - Campus:
Painting of Forum 1 and the adjacent restrooms/load center has been completed. Site Restoration Project- Campus: Restoration of the demolition site from the old KOCE building is in progress. The site, which is located on the east side of campus between the Amphitheater and Fine Arts, north of Forum 2, will remain fenced off with no public access within the fence. (See attached map [PDF] for work area)

Campus Wi-Fi Project - District:
Wireless Access Points are being upgraded throughout campus. Contractors will be on campus relocating WAPs on buildings, and boring in parking lots I and J on the Gothard side of campus this week. Crews will utilize bore rigs to bore into the ground for access to underground wires in order to connect additional antennas to the campus Wi-Fi. Boring contractors will delineate the work areas in the parking lots with cones and temporary fencing; parking is allowed in the parking lots, but away from construction vehicles and coned / fenced off areas. Please use caution around construction vehicles and equipment, and avoid these areas. (See attached map [PDF] for work area)

General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.