Language Arts Complex - Measure M:
Construction activity continues with interior painting, ceiling T-bar and lighting installation, and restroom doors and hardware installation. Exterior finishing continues with exterior stucco application, and porcelain tile and terra cotta installation. Scaffolding is being removed incrementally. The building will be connected to campus electrical power this week during off hours; there should be no interruptions to the campus. The construction fence on the east side of the project is being extended into the quad area of campus to allow for site grading and construction of new sidewalks and fire lanes within the fence; there will be no pedestrian or vehicle access along the east side of the project at the south west corner of the Student Services Center. Please navigate around the east side of Student Services. Portions of Parking Lot C remain barricaded for construction traffic; there is no parking within the barricades. Expect large equipment to be delivered through the parking lot for site work. Roads and walkways within any fenced off construction areas are not accessible to pedestrian traffic; please use alternate routes to get around Campus. Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be low to moderate for these activities. (See attached map [PDF] for work areas and construction vehicle routes)
Site Restoration Project - Campus:
Restoration of the demolition site from the old KOCE building is in progress. The site, which is located on the east side of campus between the Amphitheater and Fine Arts, north of Forum 2, will remain fenced off with no public access within the fence. (See attached map [PDF] for work area)
Pool Replastering Project - Campus:
The replastering of the swimming pools on campus continues this week. This will have minimal impact on the campus at this time. (See attached map [PDF] for work area)
General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.