Language Arts Complex - Measure M:
Construction activity continues with interior drywall installation, priming and painting, and Ceiling T-bar installation. Exterior finishing continues with stucco application and exterior porcelain tile, metal panels, terra cotta, and glazing installation. Scaffolding is being removed incrementally. There will be some work done this week in two manholes just north of the site outside the fencing (in front of and behind the Bookstore). When the manhole covers are open, they will be clearly delineated and supervised to prevent pedestrian injuries. Please avoid these areas when the manholes are occupied. Portions of Parking Lot C remain barricaded for construction traffic; there is no parking within the barricades. Roads and walkways within any fenced off construction area are not accessible to pedestrian traffic; please use alternate routes to get around Campus. Exercise caution around construction vehicles and areas surrounding the construction site, especially later in the afternoon as it is getting dark earlier. Noise level will be moderate for these activities. (See attached map [PDF] for work areas and construction vehicle routes)
Site Restoration Project - Campus:
Restoration of the demolition site from the old KOCE building is in progress. The site, which is located on the east side of campus between the Amphitheater and Fine Arts, north of Forum 2, will remain fenced off with no public access within the fence. (See attached map [PDF] for work area)
Pool Replastering Project - Campus:
The replastering of the swimming pool on campus continues this week. This will have minimal impact on the campus at this time. (See attached map [PDF] for work area)
Technology Building Roof Project - Campus:
Work on the new roof will begin this week with the tear off on Tuesday. Please avoid walking near/around the Technology building and exercise caution around construction vehicles. (See attached map [PDF] for work area and construction vehicle routes)
General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.