Language Arts Complex - Measure M:
Construction activity continues this week with interior and exterior wall framing, and installation of exterior drywall. Large deliveries including ductwork and door frames are expected intermittently throughout the week. Trucks will enter and exit off of Goldenwest Street and move through the barricaded area in Parking Lot C, accessing the construction site via the construction gate between the Math & Science bldg. and the LRC. Please mind flagmen and parking lot barricades, and avoid these areas. There is no parking within the barricades. Roads and walkways within any fenced off construction area are not accessible to pedestrian traffic; please use alternate routes to get around Campus. Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be moderate for these activities. (See attached map [PDF] for work areas and construction vehicle routes)
KOCE Demolition Project - Campus:
Abatement of the old KOCE building has been completed and demolition will be forthcoming soon. The site is located between the Amphitheater and Fine Arts, and north of Forum 2, on the east side of campus. There is no public access inside the construction fence. (See attached map [PDF] for work areas and construction vehicle routes)
General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.