Language Arts Complex - Measure M:
Drilling for deep foundation piles and installation of rebar cages within the construction site is complete. Expect increased construction traffic early in the week as drilling equipment is moved out and grading equipment is brought in, entering and exiting off of Goldenwest Street and moving through Parking Lot C. Vehicles will access the construction site via the construction gate between the Math & Science bldg. and the LRC. Please mind flagmen and parking lot barricades, and avoid this area. There is no parking within the barricades. Roads and walkways within the fenced off construction site are not accessible to pedestrian traffic; please use alternate routes to get around Campus.
Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be moderate for these activities. (See attached map [PDF] for work areas and construction vehicle routes)
Cosmetology Upgrade - Campus:
Restoration work on the Cosmetology Building upgrade has been completed. Expect Delivery Vehicle traffic in coming weeks for casework and fixtures.
General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.